Francois Lake Road - Fraser Lake Road to Birch Bay Road

Prince George, British Columbia

completeHighways and RoadsISF
Federal contribution
$559,608
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 9, 2010(actual)
Construction end
Oct 28, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 1, 2010
  • Construction end5 months earlyforecast Mar 31, 2011

Also in Prince George

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41218 in the federal list. How to read these figures.