Highway 3 Resurfacing - Elko Overhead to Fernie Ski Hill Road
Federal contribution
$2.5M
$2,475,000
Federal share50%
of $5.0M total eligible cost; the rest comes from other partners.
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Sep 10, 2010(actual)
- Construction end
- Oct 15, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 1, 2010
- Construction end2 weeks lateforecast Oct 1, 2010