Fernie - Fernie Valley Pathway - Segment 1B

Fernie, British Columbia

completeActive TransportationCVRIS
Federal contribution
$1.2M
$1,217,400
Federal share80%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2021
202220232024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Fernie
Construction start
Aug 15, 2022(actual)
Construction end
Dec 23, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 1, 2022