James White Well

Fernie, British Columbia

completeDrinking WaterSCF
Federal contribution
$826,258
Federal share33%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 24, 2015
201620172018
Built

Approved 3 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Fernie
Construction start
Oct 5, 2016(actual)
Construction end
Dec 15, 2017(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 8, 2016
  • Construction end2 months lateforecast Oct 13, 2017

Also in Fernie