James White Well
Federal contribution
$826,258
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 24, 2015
201620172018
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Fernie
- Construction start
- Oct 5, 2016(actual)
- Construction end
- Dec 15, 2017(actual)
Against the original forecast
- Construction start8 weeks lateforecast Aug 8, 2016
- Construction end2 months lateforecast Oct 13, 2017
Also in Fernie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46168 in the federal list. How to read these figures.