Asbestos Removal at Prescotts Water and Wastewater Treatment Facilities
Federal contribution
$38,333
Federal share33%
of $115.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
2011
Built
Approved 9 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Prescott
- Construction start
- Jan 17, 2011(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction end8 weeks lateforecast Feb 1, 2011
Also in Prescott