Rehabilitation of Access Road - Hay River Reserve
Hay River, Northwest Territories
Federal contribution
$230,000
Federal share29%
of $800.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2011
2011
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Northwest Territories
- Construction start
- Sep 14, 2010(actual)
- Construction end
- Feb 28, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 17, 2010
- Construction end4 months lateforecast Oct 31, 2010