Trail Development - Graves Island Provincial Park
Federal contribution
$100,000
Federal share50%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2011
2011
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Nova Scotia
- Construction start
- Jan 3, 2011(actual)
- Construction end
- Aug 31, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Dec 15, 2010
- Construction end2 weeks lateforecast Aug 15, 2011
Also in Lunenburg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41662 in the federal list. How to read these figures.