Main Street Repairs Phase 1 - Glace Bay

Glace Bay, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$28,906
Federal share26%

of $110.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2011
2011
Built

Approved 3 months before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Nov 15, 2010(actual)
Construction end
Dec 16, 2010(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Oct 11, 2010
  • Construction end3 months earlyforecast Mar 31, 2011