Interpretive Renewal Project Phase II
Federal contribution
$629,797
Federal share80%
of $787.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
202220232024
Built
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Cape Breton Miners Foundation
- Construction start
- Jan 1, 2023(actual)
- Construction end
- Jun 19, 2024(actual)
Against the original forecast
- Construction start12 months lateforecast Jan 1, 2022
- Construction end3 weeks lateforecast May 31, 2024
Also in Glace Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61455 in the federal list. How to read these figures.