Seaview Manor - Personal Protective Equipment Storage Addition
Federal contribution
$267,219
Federal share80%
of $334.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Seaview Manor
- Construction start
- Oct 8, 2021(actual)
- Construction end
- Aug 11, 2022(actual)
Against the original forecast
- Construction end4 months lateforecast Mar 31, 2022
Also in Glace Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60428 in the federal list. How to read these figures.