Upgrades to South Shore Roadway - Phase 3
Federal contribution
$485,751
Federal share49%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2011
2011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Vancouver Fraser Port Authority
- Construction start
- Oct 18, 2010(actual)
- Construction end
- May 13, 2011(actual)
Against the original forecast
- Construction start7 weeks lateforecast Aug 30, 2010
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit Fleet Expansion - SkyTrain Network$44.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41778 in the federal list. How to read these figures.