Winnipeg Convention Centre Expansion and Renovation
Federal contribution
$46.6M
$46,646,667
Federal share29%
of $161.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2012
2013201420152016
Built
Approved 2 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Winnipeg Convention Centre Corporation
- Construction start
- Jul 2, 2013(actual)
- Construction end
- Feb 29, 2016(actual)
Against the original forecast
- Construction end3 months lateforecast Nov 30, 2015
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 43134 in the federal list. How to read these figures.