Connection of well in Cap-de-la-Madeleine sector to des Érables reserve
Federal contribution
$228,735
Federal share11%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
201420152016
Built
Approved 3 years before the announcement.
- Program
- Building Canada Fund - Large Urban Centres Component
- Ultimate recipient
- City of Trois-Rivières
- Construction start
- Mar 13, 2013(actual)
- Construction end
- Apr 10, 2015(actual)
Against the original forecast
- Construction start7 months earlyforecast Oct 1, 2013
- Construction end6 months lateforecast Oct 1, 2014
Also in Trois-Rivières