Back to projects

Connection of well in Cap-de-la-Madeleine sector to des Érables reserve

Trois-Rivières, Quebec

completeDrinking WaterLUCC
Federal contribution
$228,735
Federal share11%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
201420152016
Built

Approved 3 years before the announcement.

Program
Building Canada Fund - Large Urban Centres Component
Ultimate recipient
City of Trois-Rivières
Construction start
Mar 13, 2013(actual)
Construction end
Apr 10, 2015(actual)

Against the original forecast

  • Construction start7 months earlyforecast Oct 1, 2013
  • Construction end6 months lateforecast Oct 1, 2014