Hamilton 403 Resurfacing
Federal contribution
$5.4M
$5,362,627
Federal share50%
of $10.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 15, 2013
ApprovedAug 21, 2013
20142015
Built
Approved 5 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Ontario
- Construction start
- Jan 1, 2014(actual)
- Construction end
- Dec 11, 2014(actual)
Against the original forecast
- Construction start12 months lateforecast Jan 1, 2013
- Construction end11 months earlyforecast Oct 31, 2015
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44269 in the federal list. How to read these figures.