Back to projects

Complementary works to filtration plant

Trois-Rivières, Quebec

completeDrinking WaterLUCC
Federal contribution
$976,647
Federal share25%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20142015201620172018
Built

Approved 2.8 years before the announcement.

Program
Building Canada Fund - Large Urban Centres Component
Ultimate recipient
City of Trois-Rivières
Construction start
Jun 25, 2013(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start2 months earlyforecast Sep 9, 2013
  • Construction end3.9 years lateforecast May 15, 2014

Also in Trois-Rivières

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44288 in the federal list. How to read these figures.