Squamish River Dike Raising - Phase 2
Federal contribution
$603,497
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 2, 2014
20152016
Built
Approved 5 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- District of Squamish
- Construction start
- Apr 13, 2015(actual)
- Construction end
- Mar 31, 2016(actual)
Against the original forecast
- Construction start4 months lateforecast Dec 1, 2014
- Construction end5 weeks lateforecast Feb 28, 2016
Also in Squamish
- Brennan Park Recreation Centre Retrofit and Upgrade$11.8M
- Squamish - Brennan Park Recreation Centre Building Envelope Upgrade$5.7M
- Squamish - Mamquam Wastewater Treatment Plant Upgrade$4.0M
- Squamish - Xwu'nekw Park Sea Dike at Mamquam Blind Channel$2.2M
- Squamish River Dike Raising - Upper Jimmy Jimmy (Judd) Slough$2.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44870 in the federal list. How to read these figures.