Hope - Wastewater Treatment Plant Outfall Protection
Federal contribution
$115,092
Federal share25%
of $461.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 2, 2014
20152016
Built
Approved 5 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- District of Hope
- Construction start
- Aug 25, 2014(actual)
- Construction end
- Mar 31, 2016(actual)
Also in Hope