Improvements of Acadie/Amirault Street (route 106)

Dieppe, New Brunswick

completeHighways and RoadsNRP
Federal contribution
$4.1M
$4,094,922
Federal share31%

of $13.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 17, 2015
20162017201820192020
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
City of Dieppe
Construction start
May 18, 2015(actual)
Construction end
Oct 31, 2019(actual)

Against the original forecast

  • Construction end23 months lateforecast Nov 30, 2017

Also in Dieppe

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45865 in the federal list. How to read these figures.