Improvements of Acadie/Amirault Street (route 106)
Federal contribution
$4.1M
$4,094,922
Federal share31%
of $13.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 17, 2015
20162017201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- City of Dieppe
- Construction start
- May 18, 2015(actual)
- Construction end
- Oct 31, 2019(actual)
Against the original forecast
- Construction end23 months lateforecast Nov 30, 2017
Also in Dieppe
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45865 in the federal list. How to read these figures.