Back to projects

Dieppe Intergenerational Community Complex

Dieppe, New Brunswick

completeRecreationNRP
Federal contribution
$9.6M
$9,575,632
Federal share33%

of $28.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 28, 2018
20192020
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
City of Dieppe
Construction start
Jan 9, 2019(actual)
Construction end
Oct 1, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast Oct 1, 2018
  • Construction end6 months lateforecast Apr 1, 2020

Also in Dieppe

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51981 in the federal list. How to read these figures.