Dieppe Synthetic Sports Field
Federal contribution
$2.1M
$2,080,000
Federal share52%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 29, 2021
2022
Built
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Dieppe
- Construction start
- May 2, 2022(actual)
- Construction end
- Sep 15, 2022(actual)
Against the original forecast
- Construction end6 weeks lateforecast Aug 5, 2022