Back to projects

Renovation work on the infrastructure of several streets in the City of Repentigny

Repentigny, Quebec

completeDrinking WaterCC
Federal contribution
$1.1M
$1,067,519
Federal share33%

of $3.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
201620172018
Built

Approved 9 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Repentigny
Construction start
Jun 11, 2015(actual)
Construction end
Sep 20, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2015
  • Construction end2.7 years lateforecast Dec 31, 2015

Also in Repentigny

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45904 in the federal list. How to read these figures.