Construction of an auditorium

Repentigny, Quebec

completeCultureSCF
Federal contribution
$3.1M
$3,100,000
Federal share23%

of $13.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 29, 2017
20182019202020212022
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Repentigny
Construction start
Aug 8, 2017(actual)
Construction end
Jan 10, 2022(actual)

Against the original forecast

  • Construction start19 months earlyforecast Feb 25, 2019
  • Construction end13 months lateforecast Dec 14, 2020