Modernization and repair of premises on the ground floor for the clinical sector in child psychiatry
Federal contribution
$1.4M
$1,364,727
Federal share80%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de Lanaudière
- Construction start
- Apr 19, 2021(actual)
- Construction end
- Jul 17, 2023(actual)
Against the original forecast
- Construction start7 weeks lateforecast Mar 1, 2021
- Construction end5 months lateforecast Jan 31, 2023
Also in Repentigny
- Construction of an auditorium$3.1M
- Renovation work on the infrastructure of several streets in the City of Repentigny$1.1M
- Program for the renewal of drinking water and wastewater pipes$717.1K
- Program for the renewal of drinking water and wastewater pipes$422.2K
- Program for the renewal of drinking water and wastewater pipes$355.6K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58983 in the federal list. How to read these figures.