Schedule

Announced and approvedOct 16, 2014
2015201620172018
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Sep 1, 2017(actual)
Construction end
May 17, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast May 26, 2017
  • Construction end3 weeks lateforecast Apr 27, 2018