Active Transportation Design in Lockport - RM of St. Andrews MB.
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 19, 2023
2023
Built
Approved 16 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Rural Municipality of St. Andrews
- Construction start
- Jan 4, 2023(actual)
- Construction end
- Oct 3, 2023(actual)
Against the original forecast
- Construction start7 months lateforecast Jun 15, 2022
- Construction end9 months lateforecast Dec 31, 2022