Schedule
Announced and approvedJul 25, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Rural Municipality of St. Andrews
- Construction start
- May 2, 2018(actual)
- Construction end
- Sep 19, 2019(actual)
Against the original forecast
- Construction end8 weeks lateforecast Jul 26, 2019