Schedule

Announced and approvedJul 25, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
May 2, 2018(actual)
Construction end
Sep 19, 2019(actual)

Against the original forecast

  • Construction end8 weeks lateforecast Jul 26, 2019