Oakville Lagoon Expansion
Federal contribution
$135,265
Federal share33%
of $405.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 12, 2014
2015201620172018
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Portage La Prairie
- Construction start
- Jun 12, 2017(actual)
- Construction end
- Jan 2, 2018(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2017
- Construction end4 weeks lateforecast Dec 5, 2017
Also in Portage la Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46004 in the federal list. How to read these figures.