Gaspe Road Sewer Replacement - 2015
Federal contribution
$34,371
Federal share33%
of $103.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 4, 2016
2016
Built
Approved 11 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of O'Leary
- Construction start
- Oct 15, 2015(actual)
- Construction end
- Nov 5, 2015(actual)
Against the original forecast
- Construction start2 weeks lateforecast Oct 1, 2015
- Construction end4 weeks earlyforecast Nov 30, 2015
Also in O'Leary
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46013 in the federal list. How to read these figures.