Kaulbach St and Dufferin St Distribution Main Replacement

Lunenburg, Nova Scotia

completeDrinking WaterSCF
Federal contribution
$275,561
Federal share33%

of $826.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 2, 2015
2016
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Lunenburg
Construction start
Jul 18, 2016(actual)
Construction end
Oct 31, 2016(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2016
  • Construction end17 months earlyforecast Mar 31, 2018