Kaulbach St and Dufferin St Distribution Main Replacement
Federal contribution
$275,561
Federal share33%
of $826.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 2, 2015
2016
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Lunenburg
- Construction start
- Jul 18, 2016(actual)
- Construction end
- Oct 31, 2016(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2016
- Construction end17 months earlyforecast Mar 31, 2018
Also in Lunenburg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46036 in the federal list. How to read these figures.