Duke and Main St Combined Sewer Seperation
Federal contribution
$603,146
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 12, 2015
20162017
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Trenton
- Construction start
- Jul 22, 2016(actual)
- Construction end
- Jan 17, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast May 15, 2016
- Construction end14 months earlyforecast Mar 31, 2018
Also in Trenton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46044 in the federal list. How to read these figures.