Smelt brook culvert replacement
Federal contribution
$268,537
Federal share50%
of $537.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Trenton
- Construction start
- Jul 31, 2017(actual)
- Construction end
- Nov 22, 2017(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jul 15, 2017
- Construction end4 months earlyforecast Mar 31, 2018
Also in Trenton