Town of Trenton - Trenton Park Redevelopment
Federal contribution
$2.3M
$2,280,267
Federal share60%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2019
202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Trenton
- Construction start
- Aug 24, 2020(actual)
- Construction end
- Jun 30, 2022(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2020
- Construction end3 months lateforecast Mar 31, 2022