Back to projects

Town of Trenton - Trenton Park Redevelopment

Trenton, Nova Scotia

completeRecreationRNIS
Federal contribution
$2.3M
$2,280,267
Federal share60%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2019
202020212022
Built

Approved 4 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Trenton
Construction start
Aug 24, 2020(actual)
Construction end
Jun 30, 2022(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2020
  • Construction end3 months lateforecast Mar 31, 2022

Also in Trenton