New Water Storage Reservoir
Federal contribution
$968,694
Federal share33%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2015
20162017201820192020
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of St. George
- Construction start
- May 18, 2016(actual)
- Construction end
- Nov 22, 2019(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 2, 2016
- Construction end23 months lateforecast Dec 31, 2017
Also in St. George
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46054 in the federal list. How to read these figures.