Back to projects

L'Etete Road - Watermain Replacement and New Service Laterals

St. George, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$263,569
Federal share49%

of $534.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of St. George
Construction start
May 29, 2017(actual)
Construction end
Sep 4, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast Mar 1, 2017
  • Construction end13 months lateforecast Jul 26, 2019

Also in St. George

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48190 in the federal list. How to read these figures.