New Production Well #6 and Preparation Work for Rehabilitation of Well #2
Federal contribution
$240,011
Federal share40%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
201920202021
Built
Approved 12 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of St. George
- Construction start
- Apr 6, 2021(actual)
- Construction end
- Aug 31, 2021(actual)
Against the original forecast
- Construction start5 months lateforecast Oct 31, 2020
- Construction end2 months earlyforecast Oct 31, 2021