Bear River Wastewater System Extension
Federal contribution
$177,601
Federal share33%
of $532.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 26, 2015
2016201720182019
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of the County of Annapolis
- Construction start
- Jun 6, 2016(actual)
- Construction end
- Mar 28, 2019(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 1, 2016
- Construction end9 months earlyforecast Dec 31, 2019
Also in Annapolis
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46055 in the federal list. How to read these figures.