Centennial drive - wastewater / storm water separation
Federal contribution
$1.2M
$1,198,163
Federal share48%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of the County of Annapolis
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Mar 2, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2017
- Construction end13 months earlyforecast Mar 31, 2019
Also in Annapolis
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47235 in the federal list. How to read these figures.