Back to projects

Centennial drive - wastewater / storm water separation

Annapolis, Nova Scotia

completeWastewaterCWWF
Federal contribution
$1.2M
$1,198,163
Federal share48%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
Jul 1, 2017(actual)
Construction end
Mar 2, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2017
  • Construction end13 months earlyforecast Mar 31, 2019