Extension of the Church Street Sewer Main
Federal contribution
$272,800
Federal share26%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 5, 2024
20232024
Built
Approved 15 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of the County of Annapolis
- Construction start
- Jul 22, 2024(actual)
- Construction end
- Oct 18, 2024(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 1, 2024
Also in Annapolis
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65632 in the federal list. How to read these figures.