Back to projects

Garden Creek Outfall Extension

Fredericton, New Brunswick

completeWastewaterSCF
Federal contribution
$158,971
Federal share33%

of $476.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 26, 2015
20162017
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Fredericton
Construction start
Jul 24, 2017(actual)
Construction end
Oct 28, 2017(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 3, 2017
  • Construction end4 weeks lateforecast Sep 29, 2017

Also in Fredericton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46062 in the federal list. How to read these figures.