Back to projects

Wastewater system improvements - pumping station SP5

Lamèque, New Brunswick

completeWastewaterSCF
Federal contribution
$397,169
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2015
201620172018201920202021
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Lamèque
Construction start
Sep 12, 2016(actual)
Construction end
Nov 3, 2020(actual)

Against the original forecast

  • Construction end3.3 years lateforecast Jul 31, 2017

Also in Lamèque

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46077 in the federal list. How to read these figures.