Wastewater System Upgrades - Lamèque
Federal contribution
$1.8M
$1,776,000
Federal share40%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 17, 2022
2023202420252026
BuiltForecast
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Lamèque
- Construction start
- Jul 18, 2023(actual)
- Construction end
- Jul 31, 2026(forecast)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2023
Also in Lamèque
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63520 in the federal list. How to read these figures.