Back to projects

Replacement of Stations 1 and 4 and ultraviolet (UV) Treatment of Wastewater

Lamèque, New Brunswick

completeWastewaterCWWF
Federal contribution
$704,649
Federal share50%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Lamèque
Construction start
Jul 31, 2017(actual)
Construction end
May 5, 2020(actual)

Against the original forecast

  • Construction end6 months earlyforecast Oct 31, 2020

Also in Lamèque

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48245 in the federal list. How to read these figures.