Replacement of Stations 1 and 4 and ultraviolet (UV) Treatment of Wastewater
Federal contribution
$704,649
Federal share50%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
2017201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Lamèque
- Construction start
- Jul 31, 2017(actual)
- Construction end
- May 5, 2020(actual)
Against the original forecast
- Construction end6 months earlyforecast Oct 31, 2020
Also in Lamèque