Mill Creek Culvert - Pine Glen Road

Riverview, New Brunswick

completeDisaster MitigationSCF
Federal contribution
$313,544
Federal share28%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 14, 2015
2016
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Riverview
Construction start
Jul 4, 2016(actual)
Construction end
Aug 31, 2016(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 6, 2016

Also in Riverview

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46083 in the federal list. How to read these figures.