Community Sewer System Improvements

Golden, British Columbia

completeWastewaterSCF
Federal contribution
$461,208
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
2016201720182019
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Golden
Construction start
Sep 7, 2017(actual)
Construction end
Mar 11, 2019(actual)

Against the original forecast

  • Construction start13 months lateforecast Aug 22, 2016
  • Construction end3 weeks earlyforecast Mar 31, 2019

Also in Golden

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46095 in the federal list. How to read these figures.