Federal contribution
$461,208
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
2016201720182019
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Golden
- Construction start
- Sep 7, 2017(actual)
- Construction end
- Mar 11, 2019(actual)
Against the original forecast
- Construction start13 months lateforecast Aug 22, 2016
- Construction end3 weeks earlyforecast Mar 31, 2019
Also in Golden
- Kicking Horse Canyon Project Phase 4: West Portal to Yoho Bridge$215.2M
- Kicking Horse Canyon Highway Improvement Project - Phase 2$62.5M
- Trans-Canada Highway 1 - Quartz Creek$49.9M
- Highway 1 Selkirk Mountain Four-Laning$31.5M
- TOWN OF GOLDEN: FLOOD RESILIENCE HIGHWAY 95, KICKING HORSE I & II BRIDGE$28.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46095 in the federal list. How to read these figures.