Blakeburn Lagoons Sanitary Settling Pond Remediation
Port Coquitlam, British Columbia
Federal contribution
$833,191
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2015
201620172018
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Port Coquitlam
- Construction start
- Mar 29, 2017(actual)
- Construction end
- Jul 18, 2018(actual)
Against the original forecast
- Construction start3 months earlyforecast Jul 3, 2017
- Construction end3 months lateforecast Apr 30, 2018