Washington Water Main Replacement
Federal contribution
$1.1M
$1,090,850
Federal share33%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 13, 2015
2016
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Rossland
- Construction start
- May 2, 2016(actual)
- Construction end
- Oct 28, 2016(actual)
Also in Rossland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46104 in the federal list. How to read these figures.