Spokane Street Infrastructure Improvement

Rossland, British Columbia

completeDrinking WaterCWWF
Federal contribution
$2.2M
$2,188,029
Federal share50%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Rossland
Construction start
Sep 11, 2017(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2017
  • Construction end5 months lateforecast Oct 31, 2017