Spokane Street Infrastructure Improvement
Federal contribution
$2.2M
$2,188,029
Federal share50%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Rossland
- Construction start
- Sep 11, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2017
- Construction end5 months lateforecast Oct 31, 2017
Also in Rossland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49763 in the federal list. How to read these figures.