City of Rossland Water Treatment Plant Improvements
Federal contribution
$1.0M
$1,026,000
Federal share40%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 27, 2019
202020212022
Built
Approved 2 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Rossland
- Construction start
- Oct 16, 2020(actual)
- Construction end
- Oct 14, 2022(actual)
Against the original forecast
- Construction start2 weeks lateforecast Oct 1, 2020
- Construction end2 months earlyforecast Dec 15, 2022