Westshore Parkway Completion

Langford, British Columbia

completeHighways and RoadsSCF
Federal contribution
$7.5M
$7,450,856
Federal share33%

of $22.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 22, 2015
201620172018201920202021
Built

Approved 3 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Langford
Construction start
Dec 14, 2015(actual)
Construction end
Dec 31, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast Aug 15, 2015
  • Construction end12 months lateforecast Dec 20, 2019