Trans-Canada Highway 1 Four-Laning and Median Barrier: Leigh Rd to West Shore Parkway
Federal contribution
$4.8M
$4,750,000
Federal share41%
of $11.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 23, 2019
2020
Built
Approved 2 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- British Columbia Ministry of Transportation and Infrastructure
- Construction start
- Aug 22, 2019(actual)
- Construction end
- Nov 6, 2020(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Sep 9, 2019
- Construction end5 months earlyforecast Mar 31, 2021
Also in Langford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52966 in the federal list. How to read these figures.